Site Map
St. Pat's Web > Welcome Page > News > Redevelopment

See also
on the Foundation Site
Campaign for a New St. Pat's

Redevelopment

Linda Chaplin, President & CEO St. Patrick's Home

.
Fall 2010

We have been enriched through strengthened relationships with our redevelopment supporters and continue to achieve various required approvals. The official fundraising launch took place Oct. 4th and 5th and background work with city and provincial officials is well underway.
We are aiming for a ceremonial groundbreaking event on St. Patrick’s Day March 17th, 2011 and actual shovels in the ground later in the spring. In the meantime, fine-tuning of budget figures and detailed planning continues as we match our expectations to available funds.

July 2010


I am pleased to provide the following summary of progress with St. Patrick’s Home’s redevelopment. 

*   Cost Consultant, Architectural, Gerontological and Project Management Services have been contracted using Requests for Proposal (RFP) or Requests for Expression of Interest (RFEI) methodology

*   Committee of Adjustment approval for minor variance from the City of Ottawa is in place

*   Geotechnical, Land, Tree, Noise, Traffic, Underground Services surveys among others have been completed or are in process

*    Application for funding is in process with Infrastructure Ontario (I.O.). Through  favourable 25-year debenture rates, equity from Foundation fundraising, further negotiations with the Ministry of Health and Long Term Care (MOHLTC) on funding conditions and annual projected contributions from operations we have achieved a desirable 1.01 debt service coverage ratio

*   Formal approval to construct a 288-bed Long Term Care Home has been received from the Ministry of Health and Long Term Care and the Champlain Local Health Integration Network

*   Value engineering by the selected Project Management firm was undertaken to reduce the size and thus the cost of the proposed building to a level acceptable to MOHLTC. Note: resident room size and space within each of the 9-32-bed Resident Home Areas (RHA) was not compromised. Private (141 sq. ft.) and Semi-Private rooms (130 sq.ft. each per resident) exceed MOH design standards. There are no ‘ward’ rooms i.e. 2 beds per room is the maximum. Each semi-private/shared room has a demising wall between the beds for privacy. 60% (173) rooms are private and 40% (115) are shared i.e. 2 persons per room

*   Approval of a borrowing resolution for capital projects by St. Patrick’s Home Board occurred at a special meeting June 22, 2010 followed by a same-day approval of the resolution by our sponsor, the Catholic Health Corporation of Ontario, in accordance with their respective policies.

*   A LEED Consultant firm has been contracted to optimize energy consumption and building sustainability

*   In consultation with User Groups, detailed schematics are nearing completion to produce estimates of a final estimate of costs that forms a vital part of the First Submission to  MOHLTC; target date - July 31, 2010

*   The formal Development Agreement was received July 7/2010 from MOHLTC’s Health Capital Investment Branch and we anticipate sign off within the required 10 business-day turnaround i.e. by July 21, 2010

*   While the First Submission is under review by MOHLTC throughout August and into the Fall of 2010, a number of concurrent tasks will be in process including Site Plan Application to the City, creation of Contract Documents and more detailed design development

*   Second Submission to MOHLTC is scheduled for December 2010

*   Building Permit application is anticipated in March 2011 following municipal Site Plan approval 

*   Tender Awards are to follow between April and mid-June 2011, with actual Construction/shovels in the ground commencing late June 2011

*   Substantial Completion of the building to occur by late August 2013

*   Commissioning to occur throughout August and completed by mid-September 2013 to move us toward MOHLTC approval and move in by mid-October, 2013

We hope to maintain full operations to serve our current residents and their families until move-in following which demolition of the existing building is likely. Although a number of alternative uses for the building have been seriously considered, any change of use would require prohibitive upgrades to meet building standards of today. Maintaining an empty building poses significant costs related to insurance, security personnel and owner risk and liability.

The longer range plan is to create a Campus of Care configured to make the highest and best use of this beautiful property and a development that continues to serve the needs of Ottawa’s seniors while respecting the history, Mission and Values of the Grey Sisters.

Thank you to supporters, generous donors and friends of St. Pat’s for helping us make this happen!

 

Spring 2010

A Short Note on Perseverance

It seems appropriate to say a few words about perseverance as it relates to our project. We persevered while we  ‘hurried up and waited’ for formal approval though another winter.

Fortunately, our Board of Directors believes as did British politician Thomas Foxwell Buxton who stated in 1833 that, “With ordinary talent and extraordinary perseverance all things are attainable.”  On the matter of perseverance, Henry Wadsworth Longfellow wisely opines that,

Perseverance is a great element of success. If you only knock long enough and loud enough at the gate you are sure to wake up somebody.”  

Many doors have be en knocked on and gates have been opened. The building blocks of costing, preliminary architectural drawings and staff and user consultations are well underway. We are confident that we are moving closer to shovels in the ground with the announcement received from Madeleine Meilleur’s office and a follow up meeting with the Capital Planning Branch of MOHLTC in late February. The funding gap between actual costs and Ministry funding was partially addressed by decreasing the proposed new building size by 20,000 sq ft from non-resident care areas. This was accomplished largely by reducing the size of basement excavation, relocating some services to the main level and reducing space allocated to public areas. As a note of reassurance, the Chapel will remain a focal point on the main floor and despite its reduced dimensions from what we currently enjoy, we are confident that residents and families will be well pleased with the design, aesthetics and functionality.

 

Fall 2009

Approvals—Status Report

Our application for redevelopment is currently being reviewed by the Champlain LHIN, the Capital Planning Branch of the Ministry of Health and Infrastructure Ontario. The target date is Nov.30/09 for their formal response. The identified mismatch between capital costs and Ministry funding has required in-depth analysis of options, strategies and opportunities. We know that what we wish for and what we can afford will continue to present challenges and require difficult decisions as we move through the various milestones of the project.

In support of our project, many of us have been operating from a principle that I like to call ‘strategic optimism.’ My ‘strategic optimism’ is based on a firm belief that a combination of faith and right-minded human energy can make all things happen. Board members from both the Home and Foundation have been unwavering in their lobbying and advocacy on our behalf. We are assured on a regular basis by officials and decision-makers at all levels that, “This project is going to happen!” Our position is significantly strengthened by behind-the-scenes supporters such as the Steering Committee of the Foundation and their substantial investment of time, talent and energy in fundraising.

 

Summer 2009

On the redevelopment front, we were encouraged by remarks given at our Annual General Meeting on May 28th by John Fraser, Premier McGuinty’s representative in Ottawa. On June 17, 2009 the City’s Committee of Adjustment application for minor variance was approved, completing one more step of the process. The formal Ministry of Health application is due July 31/09 with approvals anticipated in early Fall 2009.

We continue redevelopment work on many other fronts including the proactive launch of internal Focus Groups and site tours of new long term care facilities. This will provide a frame of reference for all participants and feedback to our architect and consulting gerontologist as they design the spaces that will assure optimal placement and functionality for resident care at the new St. Pat’s. Focus Groups will continue throughout the planning stage and will broaden to include Family & Resident Council representatives, family members and other interested stakeholders.

We are asking challenging questions of our participants such as the coining of a theme such as ‘Our Voice in Change’ and how to use the naming of areas to make them less institutional and more home-like. Examples of naming might be to call the Nursing Station a ‘Communications Centre’ or ‘Care Centre’ and the Tub Room a ‘Bathing Centre’ or ‘Spa’. We value the feedback that Focus Groups bring to the design process which will also include best practices in providing care such as elements that make infection prevention and control a priority.

 

Spring 2009

On the redevelopment front, background work continues with completion of many preliminary requirements. The proposed project includes the new additional beds awarded in 2007 and our existing complement of 202 beds. The Foundation and the Home look forward to sharing more concrete details as they evolve.

Application details to redevelop the existing 202 beds were released this month by the Ministry of Health with an application deadline of July 31/09.  Ministry review of applications is scheduled to occur over the summer.

Some of the features that we plan to incorporate in a new building include:

  • A 5-storey building that will accommodate 288 long stay residents

  • 9 distinct Resident Home Areas (RHA’s) with 32 residents in each unit

  • 172 rooms or 60 % of the total will be private rooms with their own bathroom

  • 116 rooms will be shared i.e. 2 persons per room with a shared bathroom

  • Large bathing areas and a separate shower room in each resident care area

  • Each Resident Home Area with its own dining, activity and lounge space

  • Residents will be accommodated in a Care Area where co-residents have similar care needs and abilities. As care needs change, residents will be able to move to an appropriate care area within the Home.

 

Winter 2008-2009

The Ministry of Health and Long Term care has announced the funding formula to redevelop B & C-level beds. Our work continues through the Board’s Corporate Development Committee’s ongoing liaison with Infrastructure Ontario, architectural firm Barry Hobin & Associates and the Ministry of Health among others. Board Chair Don Burke, Corporate Development Chair Ken Tammadge and Executive Director Linda Chaplin met with Ministry officials Jan.15 to review current cost estimates and reaffirm our commitment to a new affordable building to meet the needs of current and future residents.

The Foundation’s Steering Committee remains very busy soliciting solid financial support from top donors so that we can concretely demonstrate to key decision makers that St. Pat’s supporters believe in a redevelopment project.

 

Autumn 2008

The Ministry of Health and Long Term care advised us mid-summer that redevelopment approvals and accompanying funding announcements have been postponed until late Fall. The Ministry has encouraged us to continue our background preparatory work at St. Pat’s.

This background work includes:

  • Current building assessment

  • Site survey

  • Geotechnical (soils) survey

  • Cost consultation — to validate our cost projections

Throughout September and October you will see various consultants on site performing this work. The surveys are financed through St. Patrick’s Home Foundation and are required steps. The Foundation has been very busy over the summer building a steering committee and soliciting support so that we are well positioned to publicly fundraise as soon as needed approvals are announced.

 LONG TERM CARE FACILITY DESIGN

Design for new construction in Long Term Care is based on four main objectives:

  • A physical environment that contributes to the well being and overall health of residents

  • Design objectives are outcome- focused i.e. what residents want and how we link their wishes and needs with the spaces we create

  • The resident’s physical environment is part of a complex system where the resident’s behavioural, organizational and social contexts interact

  • Design criteria must be flexible to respond to resident needs today and in the future, as well as caregiver and family needs 

The design standards and functional considerations for new Long Term Care construction evolved from the above-noted design objectives. Features (among others) that we can expect in a new building will include:

  • Each Resident Home Area (RHA) will accommodate a maximum of 32 residents and will be a self contained unit for the residents in that area i.e. bedrooms, washrooms, bath and shower rooms, dining area, lounge, program/activity space, staff work space and storage space for that RHA

Requirements for each of the areas are specified in detail in the design standards.

Some of the resident bedroom and bathroom details are set out below:

  • All resident bedrooms contain either one or two beds i.e. Private or Semi-Private accommodation. A private room must have at least 130 sq. ft. of floor space excluding the space for the vestibule, washroom and closet. A semi-private bedroom must have at least 130 sq. ft. per resident (the washroom is shared for semi-privates)

  • The bedroom must allow access by caregivers to three sides of the bed i.e. to both sides and the foot

  • Every bedroom must have a barrier-free washroom; the entrance width must be at least 36 inches and accessed from within the bedroom itself. There must be a 5 foot turning circle in each resident washroom

  • Each bedroom door must be a minimum width of 44 inches

  • Each bedroom must be designed to allow 180 degrees change of direction for any care equipment in the room

  • Each bedroom must have at least one window that provides a direct view to the outdoors or to other naturally lit space from both a sitting and lying-in-bed position

  • You will note that new design standards in long term care are clearly resident focused. We look forward to feedback from staff, residents and their families through Focus Groups that will take place in advance of the detailed design work for a new St. Patrick’s Home.

Summer 2008

As we start what is predicted to be a record-setting summer, we have kept the heat on regarding approvals from the Ministry of Health for a redeveloped St. Patrick’s Home. At this writing, we still await the same vital Ministry approvals namely: 1) that we will be able to merge the new beds awarded in August/07 with our existing 202 beds and 2) precise knowledge of the funding formula.

We know that intense fundraising on our part and significant government support in the form of a capital grant are essential for us to move forward. The previous funding mechanism and amount allocated in the Ministry of Health’s 1998 new bed initiative was deemed insufficient at that time. A decade later, as one would expect, inflation factors and cost of materials have increased greatly which will bring our total projects costs for new construction to somewhere in the order of $60 million. That $60 million does not include plans for the existing building which may be demolished or perhaps enjoy a few more years for other purposes.

MINISTRY OF HEALTH REPORTED TIMELINES FOR C- BED REDEVELOPMENT- David Clarke (MOH capital planning and renewal branch) stated in mid-May/08:

Re: Timelines

  • Strategy announced last year on July 31, 2007

  • Policy & program design work through winter 2008

  • Review design standards

  • Review funding model

  • Develop allocation & selection criteria

  • Invite applications – spring/summer 2008

  • Evaluate applications – summer/fall 2008

  • Construction

 MINISTER OF HEALTH AND LONG TERM CARE SMITHERMAN – stated in Mid-May/08

Re: Capital Program

  • We want to create as much flexibility as possible in a capital program

  • The per diem may be convertible to a front-end grant to help the not-for-profit sector with mortgages

  • We want to see a re-emergence of NFP homes

 

OUR WORK TOWARDS  REDVELOPMENT

  • In order that we are prepared to start our project immediately when approvals and funding adequacy are confirmed:

  • Detailed financial projections have been undertaken and refreshed each time new information is available

  • A review of potential partnerships was commissioned.

  • Quotes for various required surveys (land, geotechnical etc.) have been solicited and received

  • Our Foundation has been working hard at garnering strong supporters among our St. Pat’s friends.

We have met with: Champlain LHIN’s Dr. Robert Cushman and Bernard  Lamontagne, Premier Dalton McGuinty’s constituency office staff John Fraser, and chief executive officer Peter Wilkinson,  city officials in the planning department, city councilor Maria McCrae, Ontario Infrastructure representative Robert Keene and with Ghislaine Malo, our capital renewal account manager at the Ministry of Health.

We have met with the Grey Sisters who have a community on our 4th floor and own the land on which we are located. Always strong supporters of the work we do and of our project, the Sisters share and support our hopes and dreams.

We have interviewed architectural firms. The firms we have interviewed are talented and experienced and the decision will not be an easy one.

A number of site visits to homes that each architectural firm has built are underway which will assist us as we narrow the field for an architect. We hope to have a decision by mid-July.

 

Spring 2008 

Redevelopment dialogue and intensive planning continues with municipal and provincial officials and decision makers.  We are seeking assurances that we can merge construction of the 96 new beds awarded in August/07 with the existing 202 bed complement in need of upgrade for a total estimated cost between $55-$60 million. The Ministry funding formula is scheduled for release in early June which could give us another go-forward point in our plans. As well, the St Patrick’s Home Foundation is poised to launch an enthusiastic ‘friend-raising/fund-raising’ campaign in support of a new building at 2865 Riverside Drive.

A meeting is scheduled with representatives of the Premier’s office in late March. Given recent coverage of the hospital bed crisis throughout the province and particularly in Champlain District, we are optimistic that our project will be given priority status and confident that we can be part of the solution.

In the meantime, as all pieces of the redevelopment puzzle come together, the residents we care for continue to amaze us with their resilience, their life stories and the network of family support and relationships they bring to enrich our work lives. A smile and a look of gratitude from a resident can inspire even the most fatigued worker and inspire them to return another day – even through sky high snow banks!! For that we count our blessings every day.

 

Winter 2007-2008

At St. Patrick's Home, the concept of living our Mission has permeated so deeply that I am already being asked how we will assure that our proposed new building will incorporate the spiritual dimensions of care as a priority.  It is important that our residents, their families, our volunteers, the Grey Sisters and our staff know that in every planning scenario contemplated for a new building, the Board is committed to a substantial Chapel as an essential requirement.

As we all know, a physical room called a Chapel does not automatically guarantee a sense of sacred space. We will have the familiar symbols from our current Chapel and our sponsor, the Catholic Health Corporation of Ontario, is developing interesting education resources to assist in maintaining and growing our already robust spiritual and religious care program.  I believe the commitment of the Leadership Team and all staff to live our core values every day will reassure the St. Pat’s family that our history and Mission will be not only be kept alive but will thrive into the future.

 

Autumn 2007

The late summer and early fall of 2007 have been full of good news. Our RFP for 96 additional beds was approved and major pieces of the puzzle towards a planned redevelopment of the remainder of our beds are falling into place. In August the Ministry of Health and Long Term Care announced their 10-year plan, commencing in the spring of 2008, to update aging facilities like St. Pat’s at the rate of 3500 beds per year. Our goal is to be first in line and to ‘marry’ our newly approved 96-beds with the existing 202 beds for a blended project for a total of 298 resident spaces. The resident home areas will be divided into units of not more than 32 persons per unit which will enable a closer match of resident interests and capabilities.

Our proposed target date for completion is year-end 2010 for a new building that will occupy the vacant green space here at 2865 Riverside Drive. The Home Board’s Corporate Development Committee continues its diligent and thorough work with the Grey Sisters, the Champlain Local Health Integration Network, the Ministry and others towards achieving required levels of approval and to secure solid funding to move our project forward.

 

August 28, 2007

As a member of the St. Pat’s extended “family” I wanted to be sure you knew about recent developments concerning our goal to redevelop St. Patrick’s Home.

In the spring of 2007, there were 4 applicants for the 96 new beds offered by the Ministry of Health and Long Term Care (MOHLTC) for Ottawa South. MOHLTC has informed us that St. Pat’s was the successful applicant for the 96 new additional beds and the Honourable George Smitherman, Minister of Health and Long Term Care visited us Monday (Aug.27/07) to share this wonderful news with us. We welcome this opportunity as an important “first step” in creating a totally new Class-A 298-bed Home for our residents.

We view our success as a huge vote of confidence in St. Patrick’s Home and a critical step in our future vision to redevelop to an enlarged, campus style setting conducive to caring for our present and future residents.  The new St. Pat’s will incorporate our proud heritage, traditions, values and Catholic roots while also looking to the future of care for individuals needing long term care.

While today the timing to achieve our overall goal is uncertain, we are further encouraged in our planning by MOHLTC’s recent commitment to redevelop C Level facilities like ours within the next ten years. We would like to be first in line!!

Updates that bring us closer to our goal will be communicated to you.  In the interim, I encourage you to contact me directly at 613.731.4660 ext. 233 or Jennifer Connolly, Managing Director of the Foundation at 613.260.2739 with any questions or ideas you may have regarding our plans.

Thank you

Linda Chaplin

 

Disclaimer Contact Comment
© 2007 St. Patrick's Home of Ottawa Inc.  All Rights Reserved
webmaster@stpats.ca